Thursday, May 26, 2006      Volume 4, Issue 21


This Week

1. Dr. Shlomo Cohen (Dr. Shlomo Cohen & Co.) examines the technology license

2. Bruce W. Ficken (Pepper Hamilton LLP) sifts through the variety of methods to calculate construction delay damages



Coming up in two weeks: Catherine Asaro (Beecher Carlson); Edmond T. Fitzgerald (Davis Polk & Wardwell)



1. Dr. Shlomo Cohen: A good technology license can be made at any time, so long as there is demand

PLI: We live, more and more in a licensing world, technology in particular. When should companies begin to contemplate licensing, and can you take us through a typical technology license?

DR. SHLOMO COHEN: Technology can be licensed in the early stage of its development, or at any stage where the technology becomes applicable.  It is possible to license technology at any stage of its business or financial activity, i.e. during manufacturing or marketing, the planning of production and distribution procedures, experimentation, evaluation of performance, or throughout research and development. 

Technology can be licensed by a number of means:  documents (e.g. work books, designs, and computer programs), instructions, equipment or any combination thereof. The license has to take into account the project stage or stages during which the technology is licensed, and the manner in which it is licensed.

In general, the agreement between the Licensor and the Licensee regarding the technology license, and the right to use it, should include the following elements:

Presentation of the Parties: The Licensor should declare that the technology he is licensing is his, or that he is authorized to license it. The Licensee should present himself and his ability to execute his obligations under the agreement.

Definition of the Licensed Property: The parties should define the property licensed: patents, trademarks, copyrights and know-how. Patent and trademark registration numbers should be indicated. Know-how and technology protected by copyrights should be defined differently: either by description in the agreement, or by annexes in which the technology is clearly defined. The parties should verify that all information given to them in relation to the license agreement is truthful and reliable.

Time: The duration of the agreement should be defined in relation to the obligations set in the agreement. The license agreement can be unlimited in time given that the Licensee undertakes certain obligations. On the other hand, the obligation to pay royalties may be limited in time. The consequences of cancellation or expiration of the agreement should be clearly defined. Time limitations set by law should be taken into account. For example, the law does not allow payment of royalties for a patent that has expired.

Place: The agreement should clearly define the territory that the license agreement relates to. The license may apply to an entire country, or part thereof, a number of countries, or the whole world. A Licensor cannot license more than he has. That is to say, if the Licensor did not register his patent in certain countries, he will not be able to license the technology in those countries.

Scope of Work: It is possible to limit the licensed technology to certain work sectors. For example, a pharmaceutical procedure may apply to human medicine or veterinary medicine, but the parties may agree that the license is valid for only one of the two.

The activities of the Licensee: The Licensee is customarily obliged to a minimum amount of activity, which is determined by a minimum amount of royalties or sales. It is also customary to define the Licensee's obligation to act in his "best efforts" in order to ensure this minimum activity.
 
Return: The return that the Licensee pays to the Licensor for the licensed technology is divided into two: a lump sum and periodical payments. If the transaction is for a complete technology transfer, then it is customary to make one lump-sum payment. In the case of a license agreement, the Licensor usually pays an initial lump sum, and royalties at a certain percentage of the return, or profits, derived from use of the technology. As for royalties; it is a common mistake to refer only to the rate of the royalties, whereas the base of the royalties should also be taken into account.

The license agreement should determine payment arrangements, dates, and clarify issues regarding foreign currencies (exchange rates, the possibility of transferring money from country to country, and so forth), taxes, fees, and other relevant expenses.

In recent years, it has become customary to add a section called "Most Preferred Licensee", meaning that the Licensor pledges that any other license he assigns will not include better conditions than those in the agreement with the present licensee. In this manner, the Licensor protects himself from inferior conditions when in competition with other Licensees. The return should differentiate between the payments made to the Licensor due to the use by the Licensee, and payments made to the Licensor due to assignments to other Licensees (sub-license).

Quality Control: The Licensor should demand that the Licensee maintain certain levels of quality regarding production, product, marketing and so forth. This is extremely important when the license agreement includes the Licensor's trademark, and also since certain laws impose liability on the Licensor for defective products of the Licensee, whether the Licensee uses the Licensor's trademark or not. In general, if the Licensor intends to take an active part, whether direct or indirect, in the application of the technology, it is advisable to include a section dealing with quality control.

Protection of the Technology: It is necessary to establish which party will take it upon itself to renew the patents, trademarks and designs; which party will act to track down infringements of rights and prevent infringements; how the parties will share policing expenses.

Improvements: It is advisable to determine how product improvements made by the parties during the period of the license agreement will be dealt with. Both parties have an interest in a mutual agreement: for example, that any improvement will automatically be included in the technology license and that it will be regulated.

Termination: When and how will the agreement terminate, expire or be subject to cancellation? What will the rights and obligations of the parties be when the agreement ends?

Disputes: The tools and instruments that will be used to clarify disputes between the parties should be determined. Arbitration should be considered. The law ruling the agreement should be agreed upon, as well as the forum. In the case of an international agreement, this element is extremely important.

Additional Elements: Exclusivity; secrecy of know-how; technical assistance, and whether on a one-occasion or continuous basis; acquisitions and sales between the parties – regarding the product produced under the license and the equipment for its production; competition between the Licensor and the Licensee; competition between the Licensee and other Licensees; mutual participation in expenses such as advertising, legal fees for infringement proceedings, approvals from different authorities; compensation for different claims (e.g. for defective products), and so forth.



2. Bruce W. Ficken: With mathematical certainty off the table, good record-keeping may be the key to any of the accepted methods of calculating construction delay damages

PLI: Damage due to construction delay is one of those calculations that seem like a mystery due to the sheer number of variables that may be involved. Yet parties manage to prove damages. So a project gets delayed. How do the parties get to a dollar amount?

BRUCE W. FICKEN: While generally, courts have not required "mathematical certainty" in proof of damages,1 some methods of proof have had more success than others in the courts. When available, actual cost data form of proof is superior to any of the methods that estimate increased costs. The United States Court of Appeals for the Federal Circuit has stated that "the preferred way for a contractor to prove increased costs is to submit actual cost data because such data "provides the court, or contracting officer, with documented underlying expenses, ensuring that the final amount of the equitable adjustment will be just that - equitable - and not a windfall for either the government or the contractor."2 While it would be ideal to contemporaneously identify and track all costs associated with a particular owner-caused delay or disruption, due to the realities of complex construction projects, it is often impractical.

Total Cost Method:  The Total Cost Method assesses damages by subtracting the total estimated cost of performance from the total actual cost of performance, assuming that the contractor is owed the difference.3 It is generally disfavored by courts and boards because of its inherent risk of potentially allowing a contractor to recover all costs arising from its performance rather than just those caused by the acts or omissions of the owner. For example, the total cost method does not account for potential inaccuracies in the original bid estimate, or contractor inefficiencies not caused by the other party's delay. Further, the pure form of the total cost method does not make any adjustments for delays caused by the contractor itself. For these reasons, courts have held that the total cost method of proving damages will only be permitted in limited circumstances, or as a "last resort."4 However, it may be used "under proper safeguards where there is no other alternative, since we recognized that the lack of certainty as to the amount of damages should not preclude recovery."5

There are four prerequisites to the use of the total cost method: "(1) the nature of the particular losses makes it impossible or highly impracticable to determine them with a reasonable degree of accuracy; (2) the plaintiff's bid or estimate was realistic; (3) its actual losses were reasonable; and (4) it was not responsible for the added expenses." 6 The party seeking damages bears the burden of demonstrating that each of the criteria has been satisfied.7 If it is able to do so, the total cost method may be used to calculate a disruption claim. But because errors in bid calculations or instances of mischarged costs can wound the contractor's credibility and keep the test from being met, the burden is a heavy one.8

Despite that the total cost method is not well received when used to calculate damages on the entire contract, it may still be useful as applied to specific scopes of work where the standards for its use could be more easily met.

Modified Total Cost Method: A version of the total cost method that is more favored is the modified total cost method, which seeks to address some of the difficulties encountered by use of the total cost method. Under the modified total cost method, adjustments are made to correct errors in the original bid, or actual costs are adjusted to exclude costs for which the owner was not responsible. By deducting for the costs that are attributable to the contractor, the contractor appears more reasonable and its calculations more credible. Yet, despite increased acceptance of the total cost method with these adjustments, because of the weak link between the impacts suffered and the loss incurred, it is still preferable to attempt to prove individual elements of damage, where possible.

In order to use the modified total cost method, the prerequisites of the total cost method must still be met.9 In Southern Comfort Builders, Inc.,10 the contractor's expert used both the modified total cost method and the measured mile approach in computing the contractor's loss of productivity damages. The government argued that by virtue of using more than one method, the contractor had shown that use of the modified total cost method was improper because it was not impracticable for the contractor to calculate its damages using an alternative method. The court found both calculations to be flawed and declined recovery.11

Even where a total cost claim is denied, the parties' right to damages is not necessarily extinguished. The court, with the benefit of a full record, will look to whether there is any reasonable basis upon which it can award damages. For example, in Lichter v. Mellon-Stuart Company,12 the court denied the plaintiff's claim for total costs on the stone contract, but nevertheless afforded the plaintiff certain damages based on the additional evidence introduced at trial.13

Measured Mile Approach:  The measured mile approach is becoming increasingly accepted and is preferable to the total cost method of calculating a claim for lost productivity because the link between the impact and actual damages can be demonstrated more readily. The calculation is performed by comparing the contractor's activities during the disrupted performance period to the same or substantially similar activities during a period of performance without disruption. After calculating the performance measurement during a non-impacted or "measured mile" period, it is then subtracted from actual performance during the impacted period. The difference in productivity, and therefore performance achieved and performance costs incurred, is the measure of damages.  

The more difficult part of the process is pinpointing an appropriate benchmark. The more similar the non-impacted work, the more reliable the comparison, so it is important that the relationship to the type of work used not be too broad. Further, if the benchmark selected is early in the project, adjustments should be made to account for effects of the learning curve so that lower productivity rates, which are normal at the start of a job, do not improperly skew the calculation. An as-bid performance rate cannot be used as this would result in the calculation mirroring the total cost method and then being subject to all its associated flaws. Common bases of attack on the validity of the benchmark rate are that the rate is unreasonable or that it was derived from a few discrete points rather than being representative. Another frequent challenge is that the work from which the performance rate was measured is too dissimilar from the disrupted work. But because it is not required that the work be identical, as long as the work being compared is substantially similar, the use of the measured mile approach will be permitted.

The benefit of using the measured mile approach is that it is based entirely on the contractor's actual performance data rather than on the contractor's planned productivity rate. For this reason, problems such as bid errors or problems with performance caused by the contractor itself that would weaken a claim calculated under the total cost method do not impact the measured mile calculation.

In Southern Comfort Builders, Inc.,14 the contractor's measured mile calculation was rejected by the court as fundamentally flawed. First, rather than comparing the contractor's unimpacted work with its own impacted work, the calculation compared the contractor's work with work performed by another contractor. Secondly, the total reached under the measured mile analysis was greater than the total reached using the total cost method. Because the result of a total cost method calculation represents the highest possible recovery to which a contractor could be entitled, the higher measured mile calculation could not have been accurate.15

"Should Cost" Estimates: When it is impossible to apply the measured mile approach because there are so many disruptions that there is no available non-impacted work to use as a benchmark, the "should cost" estimate methodology is often utilized. The should cost estimate compares the costs of labor actually incurred with what the costs should have been, absent the disruption. The estimate should not be based on the bid estimate; again, this would create the same problems as encountered in using the total cost method. Rather, the should cost estimate should based on the actual cost of similar work on a similar project. A contractor using this approach must be able to stand up to the same "substantial similarity" challenges faced when using the measured mile approach. When it is able to do so, in cases with pervasive disruptions, the should cost method of calculating inefficiency or lost productivity claims can be quite persuasive and is becoming increasingly accepted.

Expert testimony may be useful to establish should have cost production rates. However, general expert testimony will not be adequate. In order to be persuasive, the expert's rates must be sufficiently correlated with the contractor's actual rates on the job during unaffected periods, or with actual unaffected rates on other similar projects.

When it is not possible to establish a benchmark using a measured mile or should cost estimate, productivity rates published in industry sources may be used.16 As with the other methods, it is particularly important to make sure that the benchmark rate used is for work that is substantially similar to the project work performed. In addition to establishing that the estimates are applicable to the work actually performed, it is especially helpful to the success of the contractor's claim if it can also establish the overall reliability of the industry estimate utilized.

Another method for obtaining a reasonable estimate when a contractor is unable to produce actual performance rates is to perform time and motion studies that simulate as closely as possible the work performed and the conditions and disruptions under which it was performed.

Jury Verdict Method: When damages are not clearly ascertainable from the proof supplied by the contractor, but it is clear that damages are appropriate, the trier of fact may use the jury method to calculate the appropriate damages award. To do so, the trier of fact considers the various claim elements to set a total claim value, then determines which portions of the claim should not be recoverable due to their being attributable to the contractor's own inefficiencies, or other causes for which the owner is not responsible. The remaining figure represents the contractor's damages.  
 
While a claim is not necessarily destroyed by failure to prove a claim through the selected method because of the availability of the jury verdict method, the contractor must still provide enough support of the extent of the damages to enable the fact finder to make an award. Three prerequisites to use of the jury verdict method must be met. First, the contractor must show that it is entitled to compensation. Second, it must be established that there is no more reliable method for calculating damages. Third, the record must afford a basis for a fair and reasonable approximation of damages.17

Regardless of which method is applied, the availability and precision of contemporaneous records, and where used, the closer the similarity of the comparisons, the greater the likelihood of success in proving and recovering delay and disruption damages.